East Park 70 Project Update

 

Buildings 1 and 4 are nearing completion at East Park 70.  The 358,000 sf Building 1 has only site work remaining and is expected to be completed by October 7.  The state-of-the-art warehouse and distribution facility will offer tenants the following features:

 

The rear-loaded, 81,200 sf Building 4 should be completed by October 21 with painting, site work, and fire sprinkler system installation remaining.  This unique building will offer tenants the following:

 

CIG is working with the CBRE leasing team of Doug Viseur and Todd Witty to market both buildings to prospective tenants.  Interest has been strong, especially for the large building.  We currently have proposals out for the entirety of Building 1 and for more than half of Building 4.